A grassed waterway carries concentrated runoff across a field without cutting a gully. It works only while the grass is dense and the shape stays intact, so inspect it after major storms and at least twice a year.
What to check
- Vegetation: dense, healthy sod with no bare patches larger than a few feet.
- Channel shape: a shallow, wide parabolic or trapezoidal cross-section; no cutting or rills along the sides.
- Sediment: deposits that raise the channel or bury grass, especially at the upper end where field runoff enters.
- Outlet: stable, with no scour, and a safe release into a ditch, pond or stable area.
- Crossings: machinery crossings should be wide, shallow and kept in grass.
- Woody or weed growth that interferes with flow.
- Buffers or filter strips on each side if present.
Inspection record
| Date | Waterway ID | Stand % | Erosion (depth / length) | Sediment depth | Outlet condition | Action |
|---|---|---|---|---|---|---|
When to inspect
- Spring, before field work, to check winter damage.
- After any storm that causes runoff in the field.
- Midseason, to check for weeds, machinery tracks and mowing needs.
- Fall, to check cover before winter.
Maintenance practices
Mow after nesting season to maintain dense grass, usually after mid-July in much of the Midwest, and avoid mowing too short. Do not use the waterway as a turn row or park machinery on it. Raise tillage equipment when crossing, and avoid spraying or spreading fertilizer directly into it; follow label buffer requirements.
Fix small rills promptly with soil, seed and straw or erosion blanket. Remove sediment before it buries the grass, spread it back on the field and reseed. If the channel has down-cut or a headcut is moving upstream, call NRCS for a design check rather than patching it repeatedly.
Example inspection note
April 20: stand 85 percent, thin at the upper third where tillage dust has buried grass. Rill 4 inches deep along the east edge for about 25 feet after a March storm. Outlet stable with rock apron intact. Action: scrape 3 inches of sediment from the upper end, fill the rill with topsoil, seed with the original mix and cover with straw. Re-inspect after next heavy rain and in June.
Records for programs
If the waterway was built with cost-share, ask NRCS for the operation and maintenance requirements in your contract. Keep dated photos of the stand and any repairs. Waterway standards typically require maintenance for the practice life, and failing to do so can create liability. Check your plan for the minimum width and any seeding mix required, and keep seed tags from repairs.
Authoritative references
- USDA NRCS Soil Health
- USDA NRCS Conservation Programs
- EPA Nutrient Pollution
- USDA NIFA and Cooperative Extension
More farm stories, humor and news: farm.FM Farming.